With this change the residents of Urduliz have gained 6000 m2 of public space. Track layouts in Sopela and Plentzia are also being upgraded as a result of this work.
The replacement shuttle bus service that has been running between Plentzia and Sopela over the 24 months of the work has ceased to run today.
• With investment to the tune of €21 million and 24 months of work, the last level crossing on the Metro network has finally been eliminated.
• The new track runs below ground for 543 m, including a new underground station with a single, 6 m wide central platform shared by both tracks.”
• With this change the residents of Urduliz have gained 6000 m2 of public space. Track layouts in Sopela and Plentzia are also being upgraded as a result of this work.
• The replacement shuttle bus service that has been running between Plentzia and Sopela over the 24 months of the work has ceased to run today.